Week of March 23, 2026

Tuesday, March 24
8:00am – 4:30pm
N Harrison St to E Bush St
Directional boring
Alley between N McPherson St & N Franklin St
Drilling, trenching, and handhole installation
DA010 Service Area
Terminal drop placement and labeling (Pending approvals)
Fiber work pending approvals
Wednesday, March 25
8:00am – 4:30pm
E Bush St to N McPherson St
Directional boring
Alley between N McPherson St & N Franklin St
Drilling, trenching, and handhole installation
DA001 & DA003 Service Areas
Fiber feed cable installation (Pending approvals)
Fiber work pending approvals
Thursday, March 26
8:00am – 4:30pm
N McPherson St to E Fir St
Directional boring
Alley between N McPherson St & N Franklin St
Drilling, trenching, and handhole installation
DA011 Service Area
Fiber work (Pending DA approvals)
Fiber work pending DA approvals
Friday, March 27
8:00am – 4:30pm
E Fir St to N Franklin St
Directional boring
Alley between N McPherson St & N Franklin St
Drilling, trenching, and handhole installation
DA011 Service Area
Fiber work (Pending DA approvals)
Fiber work pending DA approvals

Week of March 30, 2026

Monday, March 30
8:00am – 4:30pm
E Bush St to E Fir St (East Alley)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Tuesday, March 31
8:00am – 4:30pm
E Fir St to N Franklin St (East Alley)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Wednesday, April 1
8:00am – 4:30pm
E Fir St to E Pine St (East Alley)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Thursday, April 2
8:00am – 4:30pm
E Pine St to N McPherson St (East Alley)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Friday, April 3
8:00am – 4:30pm
E Pine St to E Laurel St (East Alley)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation