Fort Bragg Municipal Broadband Utility Project

Last Updated: May 4, 2026

Schedule subject to change due to weather or unforeseen conditions.

Questions? Contact Carlos Hernandez, Engineering Technician, by phone at 707-961-2823 ext.130
or by email at chernandez@fortbragg.com.

Daytime Work (8am – 4:30pm)
Night Work (7pm – 5am)

Week of May 4, 2026

Friday, May 8
8:00am – 4:30pm
DA008, DA014, DA015 & ADF F-1 Areas
Conduit and utility box installation
Handhole crew off, fiber pending DA approvals

Week of May 11, 2026

Monday, May 11
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Fiber pending DA approvals
Tuesday, May 12
8:00am – 4:30pm
Eastside Alleyway to N McPherson St
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Fiber pending DA approvals
Wednesday, May 13
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Fiber pending DA approvals
Thursday, May 14
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Fiber pending DA approvals
Friday, May 15
8:00am – 4:30pm
Eastside Alleyway to N McPherson St
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Fiber pending DA approvals

Week of May 18, 2026

Monday, May 18
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Tuesday, May 19
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Wednesday, May 20
8:00am – 4:30pm
Eastside Alleyway (E Fir St to N McPherson St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Thursday, May 21
8:00am – 4:30pm
Eastside Alleyway (E Fir St to E Pine St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Friday, May 22
8:00am – 4:30pm
Eastside Alleyway (E Fir St to E Pine St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation

Schedule subject to change due to weather or unforeseen conditions.

Questions? Contact Carlos Hernandez, Engineering Technician, by phone at 707-961-2823 ext.130
or by email at chernandez@fortbragg.com.